Transportation

Site Menu  

2019 Street Maintenance Projects

The City will complete several street maintenance projects this summer. A detailed schedule will be updated here.

The work schedule can be affected by weather conditions, mechanical issues, and product availability.

Below is the list of resurfacing projects planned for this summer by treatment type:

Hot-in-place recycling
The City is using hot-in-place recycling for the following street maintenance projects. This treatment is an alternative to mill and asphalt overlay and extends the life of the pavement asset preserving the City’s investment as well as providing a new asphalt surface.

Hot-in-place recycling
Street From To Expected
start-finish date
East 8th Street Myrtle Street East of Pine Street Completed
East 9th Street Myrtle Street Ash Street Completed
East 10th Street Myrtle Street Ash Street Completed
East 10th Street College Street East of Pine Street Completed
East 11th Street Myrtle Street East of Pine Street Completed
East 13th Street Myrtle Street College Street Aug. 13
East 14th Street Myrtle Street College Street Completed
East 15th Street Church Street Walnut Street Week of Aug. 19
East 16th Street Church Street Elm Street Week of Aug. 19
East 17th Street Ash Street College Street Week of Aug. 19
East 17 ½ Street Church Street Ash Street Completed
East 18th Street Church Street Pine Street Completed
East 19th Street Church Street Walnut Street Completed
East 19½ Street Main Street Church Street Week of Aug. 19
East 20th Street Church Street Hogg Street Completed
East 21st Street Church Street Ash Street Completed
Myrtle Street East 7th Street East 11th Street Completed
Myrtle Street University Avenue East 16th Street Aug. 16
East 9½ Street Walnut Pine Street Completed
Elm Street East 7th Street East 17½ Street Completed
Ash Street East 7th Street University Avenue Aug. 14
College Street East 7th Street University Avenue Aug. 12
Walnut Street East 7th Street University Avenue Aug. 13
Hogg Street East 18th Street East 20th Street Completed
Pine Street East 7th Street University Avenue Completed
Berry Creek Drive Hwy. 195 St. Andrews TBD
Briarcrest Drive Berry Creek Drive Hamlet Circle TBD
Hamlet Circle All All TBD
Hacienda Lane All All TBD
Little Deer Trail All All TBD
Bumble Bee Drive All All TBD
Hollow Drive All All TBD
Buck Meadow Drive All All TBD
Dove Boulevard All All TBD
Pebble Creek Drive All All TBD
Drifting Meadow Drive All All TBD
Diamond Dove Trail All All TBD
Sun City Boulevard Dove Hollow Trail Whispering Winds TBD

High-performance surface seal
A sealant is applied to the surface of the roadway, reducing damage from UV radiation and vehicle traffic. The process includes a two-coat spray application of a liquid asphalt mixture. Each coat takes two to three hours to dry. Please do not walk or drive on the new sealant surface until traffic cones and barricades have been removed.

For a map of the Sun City street maintenance projects, click here.

For a map of the University Park and Raintree street maintenance projects, click here.

High-performance surface seal
Street From To Expected
start-finish date
Arrowwood Drive All All Late August/early September
Bedford Court All All Late August/early September
Bellaire Drive All All Late August/early September
Bellaire Drive All All Late August/early September
Beretta Drive All All Late August/early September
Beretta Circle All All Late August/early September
Birch Drive All All Late August/early September
Bluehaw Drive All All Late August/early September
Bowline Drive All All Late August/early September
Boxwood Loop All All Late August/early September
Briley Street All All Late August/early September
Cedar Elm Lane All All Late August/early September
Chestnut Court All All Late August/early September
Clove Hitch Drive All All Late August/early September
Concord Drive All All Late August/early September
Crown Anchor Bend All All Late August/early September
Elmwood Drive All All Late August/early September
Fairfield Court All All Late August/early September
Fairmont Drive All All Late August/early September
Green Groove All All Late August/early September
Greenside Lane All All Late August/early September
Greenside Lane All All Late August/early September
Half Hitch Trail All All Late August/early September
Hanover Court All All Late August/early September
Hickory Lane All All Late August/early September
Huisache Court All All Late August/early September
Madrid Drive All All Late August/early September
Madrone Drive All All Late August/early September
Moral Pass All All Late August/early September
Nambucca Way All All Late August/early September
Naranjo Drive All All Late August/early September
Pinon Cove All All Late August/early September
Plum Court All All Late August/early September
Poplar Drive All All Late August/early September
Rosebud Lane All All Late August/early September
Rosedale Blvd All All Late August/early September
Rowan Drive All All Late August/early September
Sheep Shank Drive All All Late August/early September
Sherwood Court All All Late August/early September
Slip Drive All All Late August/early September
Spring Court All All Late August/early September
Summers Green All All Late August/early September
Sycamore Street All All Late August/early September
Tascate Street All All Late August/early September
Village Commons Boulevard All All Late August/early September
Village Glen All All Late August/early September
Village Park Drive All All Late August/early September
Westbury Lane All All Late August/early September
Bonham Loop All All Aug. 21 and 24
Bowie Circle All All Aug. 24
Breckenridge Street All All Aug. 28
Brooks Circle All All Completed
Crocket Loop All All Aug. 21 and 24
Crosby Street All All Aug. 21
Dawson Trail All All Completed
Dickens Circle All All Aug. 21
Essex Lane All All Aug. 24 and 26
Everest Court All All Aug. 27
Falls Circle All All Aug. 21
Hale Court All All Completed
Hampton Circle All All Aug. 24
Honey Creek Trail All All Aug. 24 (from Texas Drive to Portsmouth Drive is TBD)
Hummingbird Cove All All TBD
Keystone Cove All All Aug. 27
Klonkide Drive All All Aug. 27
Lovett Cove All All Aug. 24
Lubbock Drive All All Completed
Lynne Cove All All Completed
Montley Trail All All Aug. 21
Muir Court All All Aug. 26
Nassau Circle All All Aug. 21
Nolan Drive All All Completed
Portsmouth Circle All All Aug. 24
Portsmouth Drive All All Aug. 21 and 24
Providence Street All All Aug. 26
Rainer Lane All All Aug. 26
Rushmore Cove All All Aug. 27
Scurry Pass All All Completed
Shasta Cove All All Aug. 27
Summer Road All All Aug. 26 and 28 (section from Texas to Winter drives is TBD)
Sunbird Court All All Aug. 28
Sun City Boulevard San Saba Drive Hwy. 195 Aug. 22-23
Sundance Lane All All Aug. 26
Texas Drive All All Aug. 24, and 26
Trout Lane All All Aug. 26
Vail Court All All Aug. 27
Waller Court All All Completed
Whispering Wind Drive All All Aug. 27-28
Winter Drive All All Aug. 26 and 28
Yellowstone Road All All Aug. 27
Yosemite Road All All Aug. 28
Yukon Terrace All All Aug. 26-28
Ashberry Trail All All Completed
Carol Street All All Completed
Howry Drive All All Completed
Jan Lane All All Completed
Kuykendall Drive All All Completed
McCombs Street All All Completed
McCook Drive All All Completed
Olin Cove All All Completed
Perkins Place All All Completed
Raintree Drive All All Completed
Short Street All All Completed
University Park Drive All All Completed
Waizel Lane All All Completed
Weiss Lane All All Completed