2021 Street Maintenance Projects

The City will complete several street maintenance projects this summer. A detailed schedule will be updated here.

The work schedule can be affected by weather conditions, mechanical issues, and product availability.

Below is the list of resurfacing projects planned for this summer by treatment type:

High-performance surface seal

A sealant is applied to the surface of the roadway, reducing damage from UV radiation, water, and vehicle traffic. The process includes a two-coat spray application of a liquid asphalt mixture. Each coat takes two to three hours to dry. Please do not walk or drive on the new sealant surface until traffic cones and barricades have been removed.

On the days surface seal projects are scheduled in the Old Mill Crossing, Pleasant Valley, Quail Valley, and Sun City neighborhoods, streets will be closed to through traffic and street parking from 8 a.m.-6 p.m.

Other surface seal projects in the Berry Creek, Lakeside at Lake Georgetown, and Gatlin Creek neighborhoods will close streets for 24 hours from 7 a.m.-7 a.m.

For a map of the high-performance surface seal projects in the Old Mill Crossing, Pleasant Valley, Quail Valley, and Sun City neighborhoods, click here.

For a map of the high-performance surface seal projects the Berry Creek area, click here.

For a map of the high-performance surface seal projects in the Lakeside at Lake Georgetown and Gatlin Creek neighborhoods, click here.

 

High-performance surface seal
Street From To Expected start date
Anika Cove Completed
Augusta Drive Completed
Blue Jay Court Completed
Briarcrest Drive Completed
Carmel Bay Completed
Chalk Lake Cove Completed
Chi Chi Drive Completed
Driftwood Hills Way Completed
Flat Creek Court Completed
Gatlin Creek Drive Completed
Golden Bear Drive Completed
Hays Hill Drive Completed
Kingsway Road Completed
Kingsway Road (Cul De Sac) Completed
Lake Cavern Court Completed
Lake Rim Circle Completed
Lake Spring Circle Completed
Lakeside Ranch Road Completed
Ledgemont Completed
Limestone Lake Drive Completed
Oakmont Drive Oct. 15-16
Olive Creek Completed
Owl Creek Drive Completed
Rio Vista Drive Cul-de-sac  Cul-de-sac Completed
Rock Dock Road Completed
St. Andrews Drive Completed
Spanish Dove Court Completed
Sybert Lane Completed
Tiger Woods Drive Completed
Bluebonnet Valley Drive Oct. 20
Brayden Cove Oct. 25
Britannia Boulevard Oct. 21
Canterbury Trail Oct. 22
Clover Valley Drive Oct. 21
Georgetown View Lane Oct. 25
Georgian Drive Quail Valley Drive High Tech Drive Oct. 22
Georgian Drive High Tech Drive Britannia Boulevard Oct. 21
High Tech Drive FM 1460 Georgian Drive Oct. 21
High Tech Drive FM 1460 Madison Oaks Avenue Oct. 25
Leeds Castle Walk Oct. 23
London Lane Oct. 23
Madison Oaks Avenue Oct. 25
Pleasant Valley Drive Clover Valley Lane Old FM 1460 Oct. 23
Pleasant Valley Drive Clover Valley Lane East Oct. 25
Quail Valley Drive Oct. 21 and 23
Rabbit Run Oct. 20
Silvery Valley Lane Oct. 20
Sunrise Valley Lane Valley Drive Pleasant Valley Drive Oct. 25
Sunrise Valley Lane Pleasant Valley Drive Thunder Valley Trail Oct. 20
Sunrise Valley Lane Thunder Valley Trail Valley Oaks Loop Oct. 25
Texstar Drive Oct. 22
Thunder Valley Trail Oct. 21
Thunder Valley Trail Clover Valley Lane Old FM 1460 Oct. 22
Tower Drive Oct. 21 and 23
Valley Drive Oct. 21
Valley Oaks Loop Oct. 20 and 25
Whig Way Oct. 21
Angelina Cove Completed
Apache Mountain Lane Completed
Armstrong Drive Completed
Armstrong Drive (Loop) Completed
Barrington Farm Court Completed
Beach Mountain Cove Completed
Bee Creek Court Completed
Belfalls Drive Completed
Breezeway Lane Completed
Bright Leaf Trail (northside) Sun City Boulevard Monument Hill Trail Oct. 16
Bright Leaf Trail (southside) Monument Hill Trail Sun City Boulevard Completed
Butterfly Cove Completed
Caddo Lake Trail Completed
Capote Peak Drive Completed
Caterpillar Lane Completed
Chelsea Drive Completed
Cibolo Creek Drive Completed
Cider Orchard Cove Completed
Cobalt Cove Completed
Cooper Lakes Drive Oct. 16
Copano Bay Cove Completed
Copper Breaks Drive Completed
Courtyard Garden Lane Oct. 19
Deer Hollow Trail Completed
Deer Meadow Circle Oct. 18-19
Dove Hollow Trail Oct. 18-19
Eagle Mountain Cove Completed
Emory Peak Trail Completed
Farm Hill Drive Completed
Fieldstone Drive Completed
Fort Boggy Drive Completed
Fort Griffin Trail Completed
Fox Home Lane Completed
Independence Creek Lane Completed
Lake Sommerville Trail Completed
Lindero Pass Completed
Mckinney Falls Lane Completed
Mill Creek Path Oct. 16
Monarch Trail Completed
Monument Hill Trail Bright Leaf Trail Copper Breaks Drive Oct. 16
Monument Hill Trail Copper Breaks Drive Bright Leaf Trail Completed
Moon River Drive Completed
Mountain Creek Pass Completed
Palmetto Drive Oct. 16
Piedmont Lane Completed
Potter Lane Completed
Prairie Creek Trail Completed
Prairie Grass Lane Completed
Pristine Lane Completed
Rainwater Cove Oct. 19
River Rock Drive Completed
Rosecliff Drive Completed
Salt Creek Lane Oct. 16
Salt Creek Lane (Loop) Completed
Sandy Creek Trail Oct. 16
Sea Rim Cove Completed
Silver Bonnet Drive Completed
Summer Ridge Lane Completed
Summit Street Oct. 18
Sunny Side Bend Completed
Tea Tree Cove Completed
Tips Court Completed
Whirlwind Cove Completed

Hot-in-place recycling
The City is using hot-in-place recycling for the following street maintenance projects. This treatment is an alternative to mill and asphalt overlay and extends the life of the pavement asset preserving the City’s investment as well as providing a new asphalt surface.

For a map of the hot-in-place recycling projects in downtown, click here.

For a map of the hot-in-place-recycling projects near Williams and Lakeway drives, click here.

Milling work in preparation for hot-in-place recycling street maintenance is expected to begin in mid- to late July. Once milling is completed the contractor will begin repaving streets with the hot-in-place recycling process. This is a moving operation, and streets will not be closed during repaving; however, drivers should expect delays and are encouraged to choose alternate routes. Flaggers will be present to assist drivers.

Hot-in-place recycling
Street From To Expected start date
Birch Oak Drive Lakeway Drive End TBD
Broken Spoke Trail Wagon Wheel Trail Dawn Drive Completed
Buffalo Springs Trail Wagon Wheel Trail Lakeway Drive Completed
Buttermilk Gap Street Primrose Trail Buffalo Springs Trail Completed
Cactus Trail Stagecoach Drive Arrowhead Lane TBD
Dawn Drive Broken Spoke Trail River Bend Drive Completed
Lakeway Drive Williams Drive Northwest Boulevard Paving Sept. 8-10
Lonesome Trail Wagon Wheel Trail Lakeway Drive Completed
Park Meadow Boulevard Williams Drive End Completed
Primrose Trail Wagon Wheel Trail Lakeway Drive Completed
River Bend Drive Dawn Drive Northwest Boulevard Paving Sept. 7-8
Rocky Hollow Trail Wagon Wheel Trail Lakeway Drive Completed
Wagon Wheel Trail Williams Drive Lonesome Trail Completed
Western Trail Williams Drive End Completed
Whisper Oaks Lane Lakeway Drive Cul de sac Completed
Windmill Cove Northwest Boulevard Cul de sac Paving Sept. 8
Forest Street West 11th Street West Ninth Street Paving Oct. 1
Forest Street West Seventh Street West Sixth Street Paving Oct. 1
Martin Luther King Jr. Street West 11th Street West 10th Street TBD
Martin Luther King Jr. Street West Ninth Street West Sixth Street TBD
Rock Street West 11th Street West Sixth Street Paving Sept. 29-30
Scenic Drive Just south of 10th Street Just north of Sixth Street  Paving Sept. 20-21
West 10th Street Railroad Avenue South Austin Avenue Paving Sept. 27
West Eighth Street Scenic Drive South Austin Avenue Paving Sept. 23
West Ninth Street Scenic Drive South Austin Avenue  Paving Sept. 24
West Seventh Street Martin Luther King Jr. Street South Austin Avenue  Paving Sept. 22
West Sixth Street Scenic Drive South Austin Avenue  Paving Sept. 21
West Street West 11th Street West Sixth Street Milling Sept. 9 and 10

 